Monday 3 July 2017

Brick phase update - July 2017


Brickies onsite Friday 30th June and Saturday 1st July.

The gas plumbing was also completed on 1st July, in copper - last time it was copper only at the point, but this time copper from input to point with no plastic.

The gas lines had to be installed prior to bricking commencing on RHS of house.

Brickies onsite Monday 3rd July and Tuesday 4th July.

Water leak noticed on the evening of 3rd July. Notified SSC.

Brick work completed to shoulder height around most of building.